Diploma Ministerial 49/2026 sets the working rules of the unit charged with delivering the corridor strategy, while the port runs at about a third of capacity.
The Boletim da República of 26 June 2026 carries Diploma Ministerial 49/2026, in which the Ministério da Planificação e Desenvolvimento approves the internal regulation of the Unidade Técnica de Implementação da Estratégia de Desenvolvimento Económico do Corredor de Nacala, known as UTI-PEDEC-Nacala. The document is the working rulebook of the unit that will run the strategy day to day.
The timing matters because the physical asset is already ahead of the cargo. Nacala port has installed capacity of 10 million tonnes a year and handled about 3.5 million tonnes in 2024, a 35% utilisation rate. A unit that coordinates rail, border, port and industrial-zone decisions is aimed at the gap between what the port can lift and what reaches it.
What the strategy is, and how it came back
The plan was drafted a decade ago with Japan and has been revived inside the 2025 to 2029 government programme.
President Daniel Chapo told the TICAD-9 conference in Yokohama on 21 August 2025, as AIM reported, that the government was reviving the Nacala Corridor economic development strategy first prepared with JICA more than a decade earlier. The corridor spans five provinces and links Malawi, Zambia and the Democratic Republic of Congo, and the priorities he listed were roads and bridges, railways, ports and airports, one-stop border posts and digital systems.
The strategy sits inside the 2025 to 2029 Five-Year Programme, and the implementation unit sits in the planning ministry, not in transport. Its natural job is to sequence investments made by different ministries and by CFM.
Mechanism: why a corridor needs a coordinating body
A port with spare capacity shows that the constraint sits between the assets, not inside them.
Nacala’s terminals can handle 252,000 containers a year, 2.4 million tonnes of general cargo and 3.6 million tonnes of liquids, with a channel deeper than 18 metres that needs no dredging, according to the AIM report on the port expansion tender. With 65% of capacity idle, an additional berth adds little. Cargo arrives when the railway has wagons, the border clears trucks, and the exporter in Lusaka or Lilongwe sees a lower landed cost than the alternative route.
Those levers belong to different bodies: the rail operator, the customs service, the port concession, and the neighbouring governments. A unit with written decision rights, meeting cadence and reporting lines is the mechanism that lets one body make the others’ trade-offs visible. What the diploma gives the unit, in decision rights and reporting lines, sits in its text.
The tender and the treaties make the unit a counterpart
Bidders for the port and users across three countries will deal with whatever the unit decides to prioritise.
On 10 February 2026 the Council of Ministers authorised an international tender for a concession under the Integrated Project for Expansion and Development of Nacala Port. The scope includes terminal modernisation, a special economic zone, dry ports and a floating dry dock. Bidders will price those elements on assumptions about rail links, customs procedures and land, all of which are corridor decisions.
In October 2023 Mozambique, Malawi and Zambia signed three legal instruments on managing the corridor, aimed at cutting transport cost and transit time, on the day the expanded port was inaugurated, per AIM. A domestic unit gives those treaties a Mozambican office that can be held to their timetables.
What to ask the unit for
Ask for the diploma, then for measurable corridor indicators.
Concession bidders and lenders should obtain the diploma text and read three provisions: who chairs the unit, which ministries and agencies must report to it, and whether it can direct or only recommend. They should then ask for the indicators the unit will publish, such as rail cycle time, port dwell time and border clearance time.
Shippers in Malawi and Zambia should hold their route decisions against the same indicators. The date to circle is the close of the port concession tender, because the terms offered there will show whether the unit’s priorities have reached the contract.
Sources
- Imprensa Nacional de Moçambique. “BR N.º 120 de 26.06.26, Boletim da República, I Série”. 26 June 2026. https://www.inm.gov.mz/pt-br/content/br-n%C2%BA-120-de-260626-boletim-da-rep%C3%BAblica-i-serie
- AIM (Agência de Informação de Moçambique). “Corredor de Nacala, galvanizador do desenvolvimento da África Austral – Chapo”. 22 August 2025. https://aimnews.org/2025/08/22/corredor-de-nacala-galvanizador-do-desenvolvimento-da-africa-austral-chapo/
- AIM (Agência de Informação de Moçambique). “Governo autoriza concurso internacional para expansão do Porto de Nacala”. 11 February 2026. https://aimnews.org/2026/02/11/governo-autoriza-concurso-internacional-para-expansao-do-porto-de-nacala/
- AIM (Agência de Informação de Moçambique). “Nampula / Moçambique, Malawi e Zâmbia assinam acordos para gestão do corredor de Nacala”. 7 October 2023. https://aimnews.org/2023/10/07/nampula-mocambique-malawi-e-zambia-assinam-acordos-para-gestao-do-corredor-de-nacala/